Filters
Question type

The amount shown for revenue in the planning budget for March would have been closest to:


A) $126,000
B) $140,400
C) $142,435
D) $124,200

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

The materials price variance for July is:


A) $2,100 U
B) $2,420 F
C) $2,100 F
D) $2,420 U

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

The following standards for variable manufacturing overhead have been established for a company that makes only one product: The following standards for variable manufacturing overhead have been established for a company that makes only one product:   The following data pertain to operations for the last month:   What is the variable overhead efficiency variance for the month? A) $15,550 U B) $15,200 U C) $16,530 U D) $980 F The following data pertain to operations for the last month: The following standards for variable manufacturing overhead have been established for a company that makes only one product:   The following data pertain to operations for the last month:   What is the variable overhead efficiency variance for the month? A) $15,550 U B) $15,200 U C) $16,530 U D) $980 F What is the variable overhead efficiency variance for the month?


A) $15,550 U
B) $15,200 U
C) $16,530 U
D) $980 F

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

The total standard cost per unit is closest to:


A) $55.03 per unit
B) $43.45 per unit
C) $56.52 per unit
D) $44.97 per unit

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

What is ChocO's variable overhead efficiency variance?


A) $7,260 Unfavorable
B) $10,560 Favorable
C) $31,240 Unfavorable
D) $39,050 Unfavorable

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

The total fixed cost at the activity level of 5,500 guest-days per month should be:


A) $139,700
B) $190,920
C) $244,200
D) $109,220

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

The total variable cost at the activity level of 9,300 patient-visits per month should be:


A) $114,390
B) $149,730
C) $102,090
D) $133,630

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

If variable manufacturing overhead is applied based on direct labor-hours, it is impossible to have a favorable labor rate variance and unfavorable variable overhead rate variance for the same period.

A) True
B) False

Correct Answer

verifed

verified

Krizun Industries makes heavy construction equipment.The standard for a particular crane calls for 20 direct labor-hours at $24 per direct labor-hour.During a recent period 875 cranes were made.The labor efficiency variance was $1,200 Unfavorable.How many actual direct labor-hours were worked?


A) 17,600 direct labor-hours
B) 17,450 direct labor-hours
C) 17,500 direct labor-hours
D) 17,550 direct labor-hours

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

The occupancy expenses in the flexible budget for September would be closest to:


A) $13,215
B) $12,808
C) $13,583
D) $12,880

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

When more hours of labor time are necessary to complete a job than the standard allows, the labor efficiency variance is unfavorable.

A) True
B) False

Correct Answer

verifed

verified

The labor efficiency variance for March is:


A) $3,040 U
B) $3,685 U
C) $3,685 F
D) $3,040 F

E) A) and D)
F) All of the above

Correct Answer

verifed

verified

The labor efficiency variance for July is:


A) $450 U
B) $423 F
C) $423 U
D) $450 F

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

The labor efficiency variance for May is:


A) $3,978 F
B) $4,320 F
C) $4,320 U
D) $3,978 U

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

Pittman Framing's cost formula for its supplies cost is $1,150 per month plus $11 per frame.For the month of November, the company planned for activity of 789 frames, but the actual level of activity was 792 frames.The actual supplies cost for the month was $9,480.The spending variance for supplies cost in November would be closest to:


A) $349 F
B) $382 U
C) $382 F
D) $349 U

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

The spending variance for laundry costs for the month is:


A) $5,080 F
B) $5,080 U
C) $5,800 U
D) $5,800 F

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

Warp Manufacturing Corporation uses a standard cost system for the production of its ski lift chairs.Warp uses machine-hours as an overhead base.The variable manufacturing overhead standards for each chair are 1.2 machine-hours at a standard cost of $18 per hour. During the month of September, Warp incurred 34,000 machine-hours in the production of 32,000 ski lift chairs.The total variable manufacturing overhead cost was $649,400.What is Warp's variable overhead rate variance for September?


A) $37,400 Unfavorable
B) $41,800 Favorable
C) $79,200 Favorable
D) $84,040 Favorable

E) A) and D)
F) B) and D)

Correct Answer

verifed

verified

The spending variance for "Employee salaries and wages" for March would have been closest to:


A) $3,300 U
B) $3,300 F
C) $300 U
D) $300 F

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

The materials quantity variance for September is:


A) $2,170 U
B) $2,232 U
C) $2,170 F
D) $2,232 F

E) A) and D)
F) B) and D)

Correct Answer

verifed

verified

The labor efficiency variance for July is:


A) $2,090 F
B) $2,166 U
C) $2,090 U
D) $2,166 F

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Showing 141 - 160 of 461

Related Exams

Show Answer