PERT/Cost:


A) finds the penalty costs if a project is not completed on time.
B) compares the actual budget with the planned budget.
C) shows management where to focus attention during the project.
D) a and b only.
E) b and c only.

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

The standard deviation of the critical path is equal to the sum of the standard deviations of all the activities on the critical path.

A) True
B) False

Correct Answer

verifed

verified

In an Activity-On-Node project network,the nodes are used to separate an activity from each of its immediate predecessors.

A) True
B) False

Correct Answer

verifed

verified

Project managers must often function in an environment that is beset with uncertainties.

A) True
B) False

Correct Answer

verifed

verified

An important assumption in PERT calculations is:


A) activity durations are normally distributed.
B) activity durations are independent.
C) a computer will be available to do the calculations.
D) a and b only.
E) a and c only.

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

Figure Figure   (time in days)  -What is the estimated slack time for activity A? A) 0 days. B) 20 days. C) 40 days. D) 60 days. E) 100 days. (time in days) -What is the estimated slack time for activity A?


A) 0 days.
B) 20 days.
C) 40 days.
D) 60 days.
E) 100 days.

F) A) and C)
G) A) and B)

Correct Answer

verifed

verified

In order to determine the probability of timely project completion,it is sometimes necessary to take into account paths other than the critical path.

A) True
B) False

Correct Answer

verifed

verified

Which of the following are ways of crashing an activity?


A) Using overtime.
B) Hiring more workers.
C) Using specialized equipment.
D) All of the above.
E) None of the above.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

The path in a project network with the average duration is the critical path.

A) True
B) False

Correct Answer

verifed

verified

The CPM method provides an excellent procedure for evaluating time-cost tradeoffs.

A) True
B) False

Correct Answer

verifed

verified

AON project networks have which of the following advantages over AOA networks?


A) They are easier to construct.
B) They allow the project to be completed faster.
C) They are easier to revise when there are changes in a project.
D) a and c only.
E) b and c only.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

Once a project is underway,the project manager is responsible for effectively managing:


A) the people.
B) costs.
C) time.
D) a and b.
E) a,b,and c.

F) C) and D)
G) B) and C)

Correct Answer

verifed

verified

Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17.Its slack is:


A) 0.
B) 1.
C) 4.
D) 5.
E) 9.

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

PERT/CPM can answer which of the following questions?


A) When do activities need to start and finish to meet a deadline?
B) How much delay can be tolerated for certain activities?
C) Given uncertainties,what is the probability that a project will finish on time?
D) What is the least expensive way to expedite a project to meet a deadline?
E) All of the above.

F) A) and E)
G) None of the above

Correct Answer

verifed

verified

If the variance of an activity duration is equal to 1 then all the durations are the same.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a feature of PERT/CPM?


A) An estimate of how long a project will take.
B) A graphical display of project activities.
C) An indication of crucial activities.
D) An indication of slack time.
E) All are features.

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

Figure Figure   (time in days)  -What is the estimated standard deviation in the time for activity Z? A) 2 days. B) 3 days. C) 4 days. D) 8 days. E) 5 days. (time in days) -What is the estimated standard deviation in the time for activity Z?


A) 2 days.
B) 3 days.
C) 4 days.
D) 8 days.
E) 5 days.

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Only activities on the critical path are initial candidates for crashing.

A) True
B) False

Correct Answer

verifed

verified

Figure Figure   (time in days)  -What is the estimated mean time for activity E? A) 91 days. B) 99 days. C) 100 days. D) 101 days. E) 115 days. (time in days) -What is the estimated mean time for activity E?


A) 91 days.
B) 99 days.
C) 100 days.
D) 101 days.
E) 115 days.

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

Activity C in a project network has an optimistic time estimate of five days,a most likely time estimate of seven days,and a pessimistic time estimate of nine days.Its expected duration is approximately:


A) 5 days.
B) 6 days.
C) 7 days.
D) 8 days.
E) 9 days.

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified