Filters
Question type

Study Flashcards

Which of the following variables will be at their highest expected level under a worst case scenario? I. fixed cost II. sales price III. variable cost IV. sales quantity


A) I only
B) III only
C) II and III only
D) I and III only
E) I, III, and IV only

F) B) and D)
G) D) and E)

Correct Answer

verifed

verified

You are in charge of a project that has a degree of operating leverage of 2.64. What will happen to the operating cash flows if the number of units you sell increase by 6 percent?


A) 15.84 percent decrease
B) 2.27 percent decrease
C) no change
D) 2.27 percent increase
E) 15.84 percent increase

F) B) and E)
G) B) and C)

Correct Answer

verifed

verified

Cool Shades, Inc. (CSI) manufactures biotech sunglasses. The variable materials cost is $1.69 per unit, and the variable labor cost is $3.04 per unit. Suppose the firm incurs fixed costs of $750,000 during a year in which total production is 450,000 units and the selling price is $11.50 per unit. What is the cash break-even point?


A) 76,453 units
B) 88,652 units
C) 110,783 units
D) 128,907 units
E) 140,768 units

F) None of the above
G) All of the above

Correct Answer

verifed

verified

Forecasting risk is defined as the possibility that:


A) some proposed projects will be rejected.
B) some proposed projects will be temporarily delayed.
C) incorrect decisions will be made due to erroneous cash flow projections.
D) some projects will be mutually exclusive.
E) tax rates could change over the life of a project.

F) B) and D)
G) None of the above

Correct Answer

verifed

verified

Precise Machinery is analyzing a proposed project. The company expects to sell 2,100 units, give or take 5 percent. The expected variable cost per unit is $260 and the expected fixed costs are $589,000. Cost estimates are considered accurate within a plus or minus 4 percent range. The depreciation expense is $129,000. The sales price is estimated at $750 per unit, give or take 2 percent. What is the contribution margin per unit under the best case scenario?


A) $209.52
B) $494.60
C) $469.52
D) $490.00
E) $515.40

F) A) and B)
G) B) and D)

Correct Answer

verifed

verified

Which type of analysis identifies the variable, or variables, that are most critical to the success of a particular project?


A) leverage
B) risk
C) break-even
D) sensitivity
E) cash flow

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Mr. Bear, your boss, will only agree to accept a project that, as a minimum, provides a rate of return equal to the requirement he has set for the project. Given this, explain how you can use break-even analysis to ascertain which projects will be acceptable to him as you don't want to risk hearing him growl if you waste his time presenting him with a project that is unacceptable.

Correct Answer

verifed

verified

The financial break-even quantity is the...

View Answer

What are the key features of the accounting, cash, and financial break-even points?

Correct Answer

verifed

verified

Accounting break-even: Net income =0 ;
...

View Answer

Sunset United is analyzing a proposed project. The company expects to sell 15,000 units, plus or minus 4 percent. The expected variable cost per unit is $120 and the expected fixed costs are $311,000. The fixed and variable cost estimates are considered accurate within a plus or minus 3 percent range. The depreciation expense is $74,000. The tax rate is 35 percent. The sales price is estimated at $170 a unit, plus or minus 2 percent. What is the contribution margin per unit for a sensitivity analysis using a variable cost per unit of $125?


A) $30
B) $45
C) $50
D) $24
E) $27

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

A proposed project has a contribution margin per unit of $13.10, fixed costs of $74,000, depreciation of $12,500, variable costs per unit of $22, and a financial break-even point of 11,360 units. What is the operating cash flow at this level of output?


A) $0
B) $12,500
C) $62,309
D) $74,816
E) $86,500

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

Tucker's Trucking is considering a project with a discounted payback period just equal to the project's life. The projections include a sales price of $38, variable cost per unit of $18.50, and fixed costs of $32,000. The operating cash flow is $19,700. What is the break-even quantity?


A) 631 units
B) 1,211 units
C) 1,641 units
D) 2,301 units
E) 2,651 units

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Bell Weather Goods has several proposed independent projects that have positive NPVs. However, the firm cannot initiate any of the projects due to a lack of financing. This situation is referred to as:


A) financial rejection.
B) project rejection.
C) soft rationing.
D) marginal rationing.
E) capital rationing.

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

Webster Iron Works started a new project last year. As it turns out, the project has been operating at its accounting break-even level of output and is now expected to continue at that level over its lifetime. Given this, you know that the project:


A) will never pay back.
B) has a zero net present value.
C) is operating at a higher level than if it were operating at its cash break-even level.
D) is operating at a higher level than if it were operating at its financial break-even level.
E) is lowering the total net income of the firm.

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

The degree of operating leverage is equal to:


A) the percentage change in quantity divided by the percentage change in OCF.
B) the percentage change in sales divided by the percentage change in OCF.
C) 1 + FC/OCF.
D) 1 + VC/OCF.
E) 1 - (FC + VC) /OCF.

F) B) and E)
G) C) and E)

Correct Answer

verifed

verified

Variable costs can be defined as the costs that:


A) remain constant for all time periods.
B) remain constant over the short run.
C) vary directly with sales.
D) are classified as non-cash expenses.
E) are inversely related to the number of units sold.

F) D) and E)
G) C) and D)

Correct Answer

verifed

verified

We are evaluating a project that costs $854,000, has a 15-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 154,000 units per year. Price per unit is $41, variable cost per unit is $20, and fixed costs are $865,102 per year. The tax rate is 33 percent, and we require a 14 percent return on this project. Suppose the projections given for price, quantity, variable costs, and fixed costs are all accurate to within ±\pm 14 percent. What is the worst-case NPV?


A) $984,613
B) $1,267,008
C) $1,489,511
D) $1,782,409
E) $1,993,870

F) A) and B)
G) C) and D)

Correct Answer

verifed

verified

Miller Mfg. is analyzing a proposed project. The company expects to sell 8,000 units, plus or minus 2 percent. The expected variable cost per unit is $11 and the expected fixed costs are $287,000. The fixed and variable cost estimates are considered accurate within a plus or minus 5 percent range. The depreciation expense is $68,000. The tax rate is 32 percent. The sales price is estimated at $64 a unit, give or take 3 percent. What is the net income under the worst case scenario?


A) $8,578
B) $18,228
C) $15,846
D) $20,704
E) $24,696

F) C) and D)
G) D) and E)

Correct Answer

verifed

verified

Given the following, which feature identifies the most desirable level of output for a project?


A) operating cash flow equal to the depreciation expense
B) payback period equal to the project's life
C) discounted payback period equal to the project's life
D) zero IRR
E) zero operating cash flow

F) A) and E)
G) B) and D)

Correct Answer

verifed

verified

Fixed costs:


A) change as a small quantity of output produced changes.
B) are constant over the short-run regardless of the quantity of output produced.
C) are defined as the change in total costs when one more unit of output is produced.
D) are subtracted from sales to compute the contribution margin.
E) can be ignored in scenario analysis since they are constant over the life of a project.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

What is operating leverage and why is it important in the analysis of capital expenditure projects?

Correct Answer

verifed

verified

Operating leverage is the degree to whic...

View Answer

Showing 61 - 80 of 106

Related Exams

Show Answer