Which of the following is not generally considered an advantage of specialization?


A) high productivity
B) low wage costs
C) ease of training employees
D) low equipment costs
E) all are advantages

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

D

Increasing compensation is always a way to improve worker satisfaction.

A) True
B) False

Correct Answer

verifed

verified

What is the standard time (ST) for this task if the employee worked at a twenty percent faster pace than is average, and an allowance of twenty-five percent of job time is used?


A) 20 seconds
B) 25 seconds
C) 26.7 seconds
D) 30 seconds
E) 32 seconds

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

Which of the following is not characteristic of time-based compensation plans?


A) stable labor costs
B) easier to administer than output-based plans
C) stable pay for workers
D) simpler wage computations than output-based plans
E) lower cost per unit than output-based plans

F) A) and C)
G) B) and E)

Correct Answer

verifed

verified

Which of the following is not an advantage of work sampling compared to stopwatch time study?


A) There is little or no disruption of work.
B) It is less susceptible to short-term fluctuations.
C) Workers are less resentful.
D) It is less costly and less time-consuming.
E) It is better suited for short, repetitive tasks.

F) A) and E)
G) B) and C)

Correct Answer

verifed

verified

What is the observed time (OT) for this task?


A) 81 seconds
B) 90 seconds
C) 99 seconds
D) 108 seconds
E) 540 seconds

F) A) and D)
G) B) and C)

Correct Answer

verifed

verified

A disadvantage of teams is:


A) higher quality
B) higher productivity
C) greater worker satisfaction
D) team member conflict
E) lower turnover

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The technique which can be used to estimate the percentage of time a worker or piece of equipment is idle is known as:


A) MTM
B) work sampling
C) methods analysis
D) micro motion study
E) none of these

F) All of the above
G) A) and E)

Correct Answer

verifed

verified

Which is not a requirement for an effective team?


A) talent and skills to meet goals.
B) one or more members representing supervision.
C) a system of reinforcement and celebration.
D) clearly stated and commonly held vision and goals.
E) effective and skilled interpersonal relations.

F) A) and C)
G) None of the above

Correct Answer

verifed

verified

Predetermined time standards involve the use of published data regarding how long various activities are expected to take.

A) True
B) False

Correct Answer

verifed

verified

A worker-machine chart can be used to determine how many machines an operator can manage.

A) True
B) False

Correct Answer

verifed

verified

The methods analysis chart which describes the movements of both hands at the same time is a:


A) flow process chart
B) worker-machine chart
C) gang process chart
D) simultaneous-motion (SIMO) chart
E) time/efficiency chart

F) B) and C)
G) B) and E)

Correct Answer

verifed

verified

D

The most widely used method of work measurement is work sampling.

A) True
B) False

Correct Answer

verifed

verified

How many observations should be made if he wants to be 95.44 percent confident that the maximum error in the observed time is one second?


A) 3
B) 4
C) 13.3
D) 16
E) 25

F) A) and E)
G) A) and C)

Correct Answer

verifed

verified

Which of the following concerns is not one that job designers focus on?


A) what will be done in a job
B) who will do the job
C) how the job will be done
D) when should the job be completed
E) where the job will be done

F) A) and C)
G) None of the above

Correct Answer

verifed

verified

If the person observed worked at a pace that is 80 percent of normal, what should be the normal time for this task?

Correct Answer

verifed

verified

What is the normal time (NT) for this task if the employee worked at a twenty-percent faster pace than is average?


A) 16.7 seconds
B) 20 seconds
C) 24 seconds
D) 25 seconds
E) 100 seconds

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

A work sampling study of dockworkers must be set up.There will be a large number of random observations.However, for this exercise, determine an observation schedule (arranged chronologically) for six observations.Assume workers are on the docks for eight hours a day, and that the study will be done over a 60-day period.Use the random digits listed below.

Correct Answer

verifed

verified

blured image In chronological or...

View Answer

If the person observed worked at a pace that is 20 percent faster than average, what should be the normal time for this task?

Correct Answer

verifed

verified

What is the observed time (OT) for this task?


A) 20 seconds
B) 27 seconds
C) 46 seconds
D) 66 seconds
E) 100 seconds

F) A) and D)
G) A) and B)

Correct Answer

verifed

verified

A