If an 80% curve is appropriate for a task and the first unit takes ten hours,the average time for the first two units would be eight hours.

A) True
B) False

Correct Answer

verifed

verified

A job has a 90 percent learning curve associated with it.The second unit of a 25-unit job had a unit time of 36 minutes.What will the total time be for the entire job?

Correct Answer

verifed

verified

Determine the time for the ini...

View Answer

Learning curves are mostly relevant for routine,repetitive activities.

A) True
B) False

Correct Answer

verifed

verified

For the same type of work,learning curves may differ from organization to organization.

A) True
B) False

Correct Answer

verifed

verified

A company is preparing a bid on a government contract for 40 units of a certain product.The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours,respectively.What is the appropriate learning curve?


A) 70 percent
B) 75 percent
C) 80 percent
D) 85 percent
E) 90 percent

F) D) and E)
G) C) and E)

Correct Answer

verifed

verified

According to learning curve theory,the time reduction per unit decreases as the number of units increases.

A) True
B) False

Correct Answer

verifed

verified

Learning curves generally apply to situations in which there is a high degree of human involvement,and tasks are fairly repetitive.

A) True
B) False

Correct Answer

verifed

verified

The learning percentage can be determined from a learning curve table.

A) True
B) False

Correct Answer

verifed

verified

False

A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data: A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data:   How long did it take to produce the first unit? A)  5 hours B)  6 hours C)  6.25 hours D)  6.33 hours E)  6.5 hours How long did it take to produce the first unit?


A) 5 hours
B) 6 hours
C) 6.25 hours
D) 6.33 hours
E) 6.5 hours

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

A job has an 80% learning curve.If the first unit took 40 hours to complete,the fourth unit should take roughly how many hours?


A) 20
B) 26
C) 31
D) 35
E) 40

F) None of the above
G) A) and C)

Correct Answer

verifed

verified

B

Once production is underway and the learning curve effect is occurring,successive changes made to the production process will cause the time per unit to:


A) continue following the original learning curve without any impact.
B) cause a scallop effect.
C) increase the unit time and result in a higher percentage learning curve.
D) decrease the unit time and result in a higher percentage learning curve.
E) decrease the unit time and result in a lower percentage learning curve.

F) A) and E)
G) All of the above

Correct Answer

verifed

verified

A company is preparing a bid on a government contract for 40 units of a certain product.The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours,respectively.Approximately how long will it take to produce the last ten units?


A) 33 hours
B) 69 hours
C) 45 hours
D) 38 hours
E) It is impossible to say without additional information.

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

According to learning curve theory,every doubling of total output will produce a constant percentage decrease in time per unit.

A) True
B) False

Correct Answer

verifed

verified

How long would a job with a 70 percent learning curve and a time of 20 hours for the first unit require (approximately,in hours) for the third unit?


A) 14
B) 11.4
C) 10
D) 7
E) 4

F) B) and C)
G) B) and D)

Correct Answer

verifed

verified

B

A job is expected to have a 70 percent learning curve.The first unit has been completed in 20 hours.Accordingly,the second unit can be expected to take approximately how many hours?


A) 6
B) 9.8
C) 14
D) 20
E) 34

F) C) and E)
G) B) and C)

Correct Answer

verifed

verified

Ron has noted that the first accounting problem he did in a set of similar problems took him one hour,and the ninth problem took 24 minutes. (i)Estimate Ron's learning curve. (ii)About how long did it take Ron to do his set of 10 problems?

Correct Answer

verifed

verified

(i)T1 (unit factor 9)= T9.Hence unit fac...

View Answer

Which of the following conveys the essence of learning curves?


A) As the number of units produced increase, time per unit increases.
B) As the number of units produced decrease, time per unit increases.
C) As the number of units produced increase, time per unit remains constant.
D) As the number of units produced increase, time per unit doubles.
E) As the number of units produced increase, time per unit decreases.

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data: A manager wants to analyze the learning curve associated with producing one of his company's products.Accordingly,he has gathered the following data:   What is the learning curve percentage? A)  40%. B)  50%. C)  75%. D)  80%. E)  90%. What is the learning curve percentage?


A) 40%.
B) 50%.
C) 75%.
D) 80%.
E) 90%.

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

To which worker would learning curves be most applicable?


A) Bus driver
B) Punch press operator
C) Assembly-line worker
D) Auto service mechanic
E) Laundromat operator

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

For an 80% learning curve,if the first unit requires 10 hours,the second unit will require 8 hours,and the third 6.4 hours.

A) True
B) False

Correct Answer

verifed

verified